New Brunswick released new data centre rules, while Alberta proposed new limits on large projects near homes and farmland. The moves aim to add certainty and protect electricity, water and local communities.
Key points
- New Brunswick says projects must deliver a net benefit and consult First Nations.
- NB Power had 10 applications needing up to 900 megawatts combined.
- Alberta wants future water-use limits and close to zero water use.
The full story
New Brunswick and Alberta both announced new ground rules for data centre projects this week. In Fredericton, the New Brunswick government released its data centre development policy on Thursday and said projects that do not follow the new rules will be rejected. The province also plans legislative amendments to give it power to review and approve electricity supply arrangements for data centres, with a focus on protecting existing ratepayers.
Energy Minister René Legacy said data centre proponents currently apply directly to NB Power, which does not have criteria to judge whether a project benefits the province. He said the utility now looks only at power demand and negotiates a contract. Under the new approach, the province will review the project first and only move ahead if there is a potential net benefit and no risk to the grid, rates or reliability. NB Power confirmed last month that it had 10 data centre applications that would need up to 900 megawatts of power combined.
The policy also requires developers to consult with First Nations and formalise any commitments in binding agreements. Large projects will need to register for an environmental impact assessment. Developers must minimise environmental impacts, show economic benefits and prove they are technically and financially sound. The province also proposes giving local governments the power to negotiate community benefit agreements for amenities, local hiring and in-kind benefits. Jean-Claude D’Amours said the policy will allow only projects that meet the criteria to move forward.
The same day, Alberta Technology Minister Nate Glubish announced proposed legislation to limit large data centre developments near homes and farmland. Alberta also wants future standards for water use, with the government aiming for "close to zero" water use. Glubish said the standard would be strict and would effectively prohibit evaporative cooling methods. The rules would not apply to projects that already have development permits, including Meta’s $13-billion AI data centre campus north of Edmonton. In Nova Scotia, Premier Tim Houston said the current industrial approval process is enough and that his government will not require the same environmental assessments. He said projects like EverWind Fuels’ proposed $10-billion data centre in Point Tupper must also follow federal development principles.
Why it matters
This affects where big data centres can be built, how much power they can use and what local residents may see in their communities. For Atlantic Canadian households and businesses, it could shape electricity planning, land use and local jobs tied to major projects.
Who’s affected: Data centre projects, utilities and nearby communities
What’s next
New Brunswick still needs legislative amendments, and Alberta says details on water-use standards will be finalised later through regulation. The new New Brunswick rules apply to all data centre proposals already under consideration.
What to do
- Review power and water requirements before backing a data centre project.
- Ask about consultation and community benefit commitments early.
- Check whether local approvals or environmental reviews apply.
Original reporting