New Brunswick has set new rules for proposed data centre projects and will reject those that do not fit. The province says projects must show net benefit and protect ratepayers.
Key points
- NB Power had 10 data centre applications, needing up to 900 megawatts.
- Projects must consult First Nations and prove economic benefits.
- The province will review electricity supply arrangements before projects connect.
The full story
FREDERICTON — New Brunswick released a data centre development policy and said projects that do not follow the new rules will be rejected. The province also plans legislative amendments to give it power to review and approve electricity supply arrangements for data centres, with a focus on protecting existing ratepayers.
Energy Minister René Legacy said data centre proponents are currently applying directly to NB Power, which does not have criteria to assess a project’s benefits to the province. He said the utility looks at power demand and negotiates a contract. Under the new approach, the province will look at project benefits before an application reaches the utility.
The province says data centre developments will have to provide a “net benefit” to utilities such as Crown-owned NB Power, which confirmed last month that it had 10 data centre applications that would need up to 900 megawatts of power combined. The new policy also requires developers to consult with First Nations and to formalize commitments in binding agreements. Large projects must register for an environmental impact assessment.
The rules apply to all data centre proposals, including those already under consideration. Post-Secondary Education and Training Minister Jean-Claude D’Amours said the policy will ensure projects meeting the province’s strict criteria can move forward, while those that do not will never be developed in New Brunswick. An article from another outlet said the amendments came just a day after Legacy and D’Amours unveiled a new policy framework for approval of data centres. Michelle Robichaud of the Atlantica Centre for Energy said the province has an opportunity to attract investment, but growth must benefit the province and electricity customers.
Why it matters
This could affect energy bills, local planning and investment in New Brunswick. Businesses and households may see more debate over power demand, grid reliability and whether major projects bring enough local benefit. Communities could also see new consultation and environmental requirements for large developments.
Who’s affected: New Brunswick data centre projects and electricity customers
What’s next
The province still needs to pass the planned legislative amendments. Large projects will also have to move through environmental assessment and the new approval process.
What to do
- Follow provincial approval news for major power projects.
- Review energy and land-use impacts before backing new developments.
- Ask for clear community and ratepayer benefits in consultations.
Original reporting
Not sure if this affects you?
Fundy Tech helps businesses and households across Atlantic Canada stay patched, protected and up to speed. Tell us what you’re running and we’ll tell you straight whether you need to act.