Telus is ending its role in two planned Vancouver AI data centres with Westbank after local opposition. Westbank says it will keep going with a new partner.
Key points
- Telus quits two Vancouver AI data centre projects with Westbank.
- Planned sites were downtown Vancouver and Mount Pleasant.
- Projects had 63,000 Nvidia chips and up to 163 MW planned.
- Hundreds protested over environmental, housing and community concerns.
- Westbank says it will continue with a new, unnamed partner.
The full story
Telus Corp. said it is ending its participation in two planned artificial intelligence data centres in Vancouver. The company had announced the projects in May with Vancouver-based developer Westbank Corp. The plans called for one new data centre in downtown Vancouver and another conversion of an office building in Mount Pleasant.
Telus had said the sites would eventually use about 63,000 Nvidia chips and draw up to 163 megawatts of electricity. The Mount Pleasant building was expected to open at the end of 2026, and the downtown site in 2029. Telus also signed a memorandum of understanding with the federal government, although the terms were not finalized.
A Telus spokesperson said the company has decided not to proceed, without giving a reason. A source familiar with the matter said lack of local support led Telus to reconsider. Hundreds of people protested in Vancouver during the summer over environmental, community and housing impacts.
Westbank says it will continue the projects with a new partner that has not yet been announced. One of the two Vancouver locations still needs rezoning, and a city councillor motion due in November could bring stricter requirements, including independent environmental assessments and possible fees. Telus says it will keep expanding in Kamloops and is looking at new partnerships and locations for sovereign compute capacity.
Why it matters
The projects were meant to add Canadian-controlled AI computing capacity, but public opposition has changed the plan. That shows how local concerns can reshape major tech builds in cities.
Who’s affected: Vancouver residents, Westbank, Telus, and local users of AI compute
What’s next
One Vancouver site still needs rezoning. A city councillor motion due in November could add stricter data-centre rules.
What to do
- Watch local rezoning and consultation notices.
- Expect more detail from Telus on future B.C. sites.
- Follow city council decisions if you live near the projects.
Original reporting
Not sure if this affects you?
Fundy Tech helps businesses and households across Atlantic Canada stay patched, protected and up to speed. Tell us what you’re running and we’ll tell you straight whether you need to act.